RMA Presents “The Canarsie Tunnel Project”
-
Greenwich Sentinel·
- April 8, 2025·
The Canarsie Tunnel repair project, undertaken after significant damage from Superstorm Sandy in 2012, exemplified innovative engineering and collaboration to minimize disruption for L train riders. Originally planned as an 18-month full shutdown, the project was reimagined into a 15-month effort maintaining partial operation, utilizing Fiber Reinforced Polymer (FRP) panels and a new cable racking system for efficient repairs. Completed three months ahead of schedule, the project not only saved costs but also set a precedent for modern infrastructure resilience and repair strategies.