PHOTOS: New Lebanon School December Construction Update

By Richard Kaufman

On Monday, the New Lebanon School Building Committee released its December construction update.

The following work was accomplished in the past month:

  • Driveway and Walkway Paving is now complete
  • Exterior metal wall panels and glass are complete
  • All entrance doorways have been completed.

Work anticipated for the coming weeks:

  • Interior finishes to be completed: progressing from 2nd floor to 1st floor areas
  • Bathroom ceilings, wall tile and sinks
  • Classroom ceilings, light fixtures, millwork and flooring all ongoing on 2nd floor then 1st floor
  • Media center carpet
  • Doors and hardware as rooms are complete
  • Kitchen servery ceramic floor tile
  • Kitchen cooking equipment delivery after tile complete
  • Elevator installation will begin in late November.
  • Ductwork, sprinkler piping, domestic water and electrical conduit are all wrapping up
  • Interior glass will be complete
  • Gym equipment and flooring will be end of December activities

 The project has received its third reimbursement from the state of $4 million, totaling $12.2 million to date. 

The intra-district elementary International Baccalaureate magnet school will serve students in grades PreK-5. There will be a centrally located earning commons, equipped with flexible furnishings & adaptable technological infrastructure, allows for multiple zones of simultaneous learning.  The building is designed to meet the sustainability goals established by the Educational Specifications and to achieve a gold-level LEED rating from US Green Building Council.

Photos of construction below:

*all photos courtesy of NLSBC

Building North Façade and Driveway – 11/7/18
Building West Façade with Bridges – 11/21/18
Cafeteria Skylights – 11/21/18
Classroom millwork – 11/21/18
Classroom flooring – 11/21/18

 